Ball Joint: Service and Repair

INSPECTION AND REPAIR

Make necessary parts replacement if wear,

damage, corrosion or any other abnormal conditions are found through inspection.
Check the following parts:
-

Upper control arm

-

Bushing

-

Fulcrum pin

2. Inspect the lower end boot for damage or grease leak. Move the ball joint as shown in the figure to confirm its normal movement (Fig. 3C-24).

Inspect screw/taper area of ball for flaws. If any defects are found during the inspections, replace the end assembly with new one.

3. After moving the ball joint 4 or 5 times, attach nuts, then measure the preload Fig. 3C-25).

PRELOAD TORQUE, INSPECTION AND REPAIR:
Upper Link End  kg.m (lb.ft.) N.m  0.1 - 0.33 (0.7 - 2.4/0.9 - 3.2)

Lower Link End  kg.m (lb.ft.) N.m  0.5 - .35 (0.35 - 2.50/0.5 - 3.4)  

INSTALLATION
Upper Nuts final Torque N.m (ft.lb) 24 (32.4)

Lower Nuts final Torque N.m (ft.lb) 103 (76)

Nut and Cotter Pin Torque, Pick-up 4WD/Amigo  N.m (lb.ft.) Upper 98 (73) Lower 94 (127.5)

Nut and Cotter Pin Torque, Pick-up 2WD  N.m (lb.ft.) Upper 108 (80) Lower 147 (108.5)
1988-93 Pick-up/Amigo/Rodeo

PRELOAD TORQUE, INSPECTION AND REPAIR
Upper Link End  kg.m (lb.ft.) N.m  0.1 - 0.33 (0.7 - 2.4/0.9 - 3.2)

Lower Link End  kg.m (lb.ft.) N.m 0.07 - 0.65 (0.51 - 4.7/0.7 - 6.4)  

INSTALLATION
Upper Nuts final Torque N.m (ft.lb) 24 (32.4)

Lower Nuts final Torque N.m (ft.lb) 103 (76)

Nut and Cotter Pin Torque, Pick-up 4WD/Amigo  N.m (lb.ft.) Upper 98 (73) Lower 94 (127.5)

Nut and Cotter Pin Torque, Pick-up 2WD  N.m (lb.ft.) Upper 108 (80) Lower 147 (108.5)