IS 250C V6-2.5L (4GR-FSE) (2011)
Axle Hub/Installation
28. TEMPORARILY TIGHTEN REAR NO. 1 UPPER CONTROL ARM ASSEMBLY (for RH Side)
HINT
Perform the same procedure as the LH side.
29. TEMPORARILY TIGHTEN REAR NO. 2 UPPER CONTROL ARM ASSEMBLY (for LH Side) See: Control Arm/Service and Repair/Rear
Upper Arm/Installation
30. TEMPORARILY TIGHTEN REAR NO. 2 UPPER CONTROL ARM ASSEMBLY (for RH Side)
HINT
Perform the same procedure as the LH side.
31. INSTALL TOE CONTROL LINK SUB-ASSEMBLY LH See: Wheel Hub/Service and Repair/Rear Axle Hub/Installation
32. INSTALL TOE CONTROL LINK SUB-ASSEMBLY RH
HINT
Perform the same procedure as the LH side.
33. TEMPORARILY TIGHTEN REAR NO. 1 SUSPENSION ARM ASSEMBLY LH See: Control Arm/Service and Repair/Rear Lower
Arm/Installation
34. TEMPORARILY TIGHTEN REAR NO. 1 SUSPENSION ARM ASSEMBLY RH
HINT
Perform the same procedure as the LH side.
35. INSTALL NO. 3 PARKING BRAKE CABLE ASSEMBLY
(a) Connect the No. 3 parking brake cable assembly to the parking brake equalizer.
(b) Install the No. 3 parking brake cable assembly to the body with the 3 bolts and 2 clamps.
Bolt (A) - Torque : 6.0 Nm (61 kgf-cm, 53 in-lbf
Bolt (B) - Torque : 19 Nm (194 kgf-cm, 14 ft-lbf
NOTICE:
Do not twist the No. 3 parking brake cable assembly when installing it.
36. INSTALL NO. 2 PARKING BRAKE CABLE ASSEMBLY
HINT
Perform the same procedure as the No. 3 parking brake cable assembly.