Page 3
background image

4.

Using clean, dry shop air only, apply air pressure of 552 kPa (80 psi) maximum to the valve on the tool. Refer to Figure 3.

5.

With air pressure applied to the valve, inspect for any air leaks at the studs, seams and pilot hub. A soap bubble solution may be applied around
those areas to aid in diagnosis. If any leaks are present, replace the converter.

6.

Disconnect the air line and release the air pressure from the tool by pulling on the release ring and then slowly releasing the press. Refer to Figure
4.