Shift Solenoid: Testing and Inspection
Shift Solenoid No. 1
INSPECTION
1. Disconnect the shift solenoid connector and measure at the sensor side.
2. Measure the resistance between terminal 6 and ground.
Standard value: 11 - 15 ohms [at 25° C (77° F)]