Workshop Manuals Factory service & repair Volkswagen
01 4 - Cyl. injection engine (1.0 l)02 5 - Speed manual gearbox 013 and 0CA03 Brake systems04 Running gear, axles, steering05 Running gear, axels, steering - GTI 16V06 Heating, air conditioning07 Electrical system08 Electrical: Communication09 General body repairs, interior10 General body repairs, exterior11 4 - Cyl. injection engine12 4-Cyl. injection engine (1.0 l, 2-valve, rocking rollers)13 4-cyl. injection engine (2-valve)14 4 - Cyl. diesel engine
Volkswagen Gol G3 with Parati and Saveiro, Brazil (1999-2005)05 · Running gear, axels, steering - GTI 16V
05 · Steering & suspension

Installing

Make
Volkswagen
Model
Gol G3 with Parati and Saveiro, Brazil
Year
1999–2005
Section
Servicing steering box - 16V chassis › Installing
Running gear, axels, steering - GTI 16VInstalling

Installing

Warning Seals of bolts that fasten steering box high pressure and oil return pipes must be renewed whenever loosened or removed.

Install steering box in the same way, side and position.

Install without tightening nut that fastens steering box (right side) to rear cross panel.

Place high pressure and oil return pipe tubes into their due housings.

Install steering track rod mountings and tighten bolts at 45 Nm.

Lift vehicle.

Install bolts that fasten steering box to left front wheel arch and tighten nuts at 20Nm.

Install left side nut that fastens steering box to rear cross panel and tighten at 40 Nm.

Install nuts that fasten steering track rods to rack and tighten at 45 Nm.

Lower vehicle.

Complete tightening of right side nut that fastens steering box to rear cross panel (previously installed) at 40 Nm.

Couple steering shaft to steering box pinion in the following way:

Couple adapter (coupling) to pinion.

Install and tighten adapter lower fastening bolt at 28 Nm. Tighten adapter upper fastening bolt at 28 Nm.

Install windscreen washer water reservoir (vehicle with ABS).

Install without tightening the two bolts that fasten steering box high pressure and oil return pipe tubes.

Install clamp that fastens high pressure pipe tube to steering box and tighten bolt at 0.5 Nm.

Tighten bolts (previously installed) of high pressure and oil return pipes at 30 Nm.

Fit ATF oil reservoir.

Install windscreen washer water reservoir bottle neck.

Supply with ATF oil, until upper mark (max) in the reservoir.

Lift vehicle and with engine stopped, turn steering wheel several times, from stop to stop, to expel air that may be in the system.

Fill ATF oil.

Run engine Turn again, several times, fully to left and right, observing and completing oil level, until it is stabilised on maximum top mark.

Warning Whenever filling or checking oil level, vehicle must be levelled and steering wheel must be in central position (aligned wheels). Never reuse drained ATF oil.

Visually check to ensure there is no oil leakage in the system and install coolant reservoir.

Install engine cover.

Parts & tools for this job For 1999 Volkswagen Gol