PINPOINT TEST C : NO POWER IN RUN |
TEST CONDITIONS | DETAILS/RESULTS/ACTIONS |
C1: CHECK THE RADIO AND CLOCK OPERATION |
| 1 Ignition switch in position I. |
| 2 Check the radio and clock operation. |
| Do the radio and clock operate? Yes No |
C2: CHECK THE IGNITION SWITCH |
| 1 Carry out the ignition switch component test, refer to the wiring diagram. |
| Does the ignition switch test OK? Yes No INSTALL a new ignition switch. REFER to the procedure in this Section. TEST the system for normal operation. |
C3: CHECK FOR OPEN ON CIRCUITS 15-DA1 (GN) AND 15-DA2 (GN/BU) |
| 1 Disconnect F10 (20A). |
| 2 Disconnect Ignition switch C456. |
| 3 Measure the resistance between the ignition switch C456 pin 4 harness side and the ignition relay C59 pin 2 in the central junction box (CJB). |
| Is the resistance greater than 10,000 ohms? Yes REPAIR the circuit 15-DA1 (GN) and 15-DA2 (GN/BU). TEST the system for normal operation. No |
C4: CHECK THE BATTERY JUNCTION BOX FUSE 10 (20A) |
| 1 CHECK . |
| 2 Check the fuse 10 (20A). |
| Is the fuse OK? Yes No INSTALL a new fuse. TEST the system for normal operation. If the fuse fails again REPAIR circuit 30-BB9 (RD). |
C5: CHECK FOR OPEN ON CIRCUIT 30-BB9 (RD) |
| 1 Disconnect Ignition switch C456. |
| 2 Measure the resistance between the ignition switch C456 pin 1 circuit 30 BB9 (RD) and fuse 10 (20A) loadside circuit 30-BB9 (RD). |
| Is the resistance less than 5 ohms? Yes INSTALL a new ignition switch. REFEr to the procedure in this section. TEST the system for normal operation. No REPAIR the circuit 30-BB9 (RD). TEST the system for normal operation. |