Removing - refitting: Balance shaft drive belt
- Make
- Citroën
- Model
- XM II Factory Workshop Manual
- Year
- 1994–2000
- Section
- Engine assembly › Removing - refitting: Balance shaft drive belt
Removing - refitting: Balance shaft drive belt
1. Recommended tools
[1] flywheel locating peg 7014-T.J (kit 7004-T).
[2] camshaft gear setting rod 5711-T.A (kit 5711-T).
[3] injection pump setting rod 5711-T.B (kit 5711-T).
[4] balance shaft setting rods 5711-T.D (kit 5711-T).
[5] belt tension measuring instrument with digital read out (SEEM).
4099-T: SEEM C.TRONIC 105.
4122-T: SEEM C.TRONIC 105.5.
[6] tensioning lever 5711-T.E (kit 5711-T).
2. Removing
Unclip the battery trim cover:
- 2 Attachment points, front side end
- 1 Attachment point marked by an arrow towards the air filter (using a screwdriver)
Disconnect the cable from the battery negative terminal.
Lift and support the vehicle with front wheels suspended.
Remove:
- The front right wheel
- The engine protection plate situated under the RH front wheelarch
- The front right mud guard
- The protective panel under the engine
- The auxiliary equipment drive belt (see the relevant operation)
- The timing belt (see the relevant operation)
Peg the balance shafts with the help of tools [4].
Remove: The tensioning roller (1).
Loosen the screw (2) to free the roller tensioner.
Remove: The belt from the balance shafts.
3. Refitting
Check if the rollers operate correctly.
Reinstall the balance shafts drive belt.
Remove the tools [4].
Attach the tool [5] to the belt.
Pre-tension the belt by means of tool [6] (located in the square hole of the roller tensioner).
Tension adjustment:
- New belt, to 40 daN (70 SEEM units)
- Used belt, to 25 daN (51 SEEM units)
Tighten the roller tensioner to 4,5 m.daN.
3.1. Verifying the fitting pre-tension
Remove and refit equipment [5] (do correct, if necessary).
Remove the tool [5].
Fit:
- The tensioning roller (1) Tighten to 4,5 daN.m
- The timing belt
Pre-tension, then tension the timing belt (see the relevant operation).
N.B.: Turn the engine 10 revolutions (if it has not been done when reinstalling the timing belt).
Loosen the screw (2) to free the roller tensioner.
Attach the tool [5] to the belt.
Adjust the belt tension by means of tool [6] (located in the square hole of the roller tensioner).
Tension adjustment:
- New belt, to 12 daN (31 SEEM units)
- Used belt, to 9 daN (26 SEEM units)
Tighten the roller tensioner to 4,5 m.daN.
3.2. Verifying the fitting tension
Remove and refit equipment [5] (do correct, if necessary).
Remove the tool [5].
4. Check
Turn the engine 2 revolutions.
Peg the flywheel, (behind the engine), by means of tool [1].
In order to ensure that no tooth has been jumped, check visually if the following components are correctly pegged:
- Injection pump
- Camshaft
- Balance shafts
Remove the tool [1].
To complete the assembling operations, refer to the timing belt removal/refitting.
Parts & tools for this job For 1994 Citroën XM
- PARTEngine gasket setSearch: Citroën XM 1994 engine gasket set
- TOOLTorque wrenchSearch: 3/8 inch torque wrench
- TOOLFeeler gauge setSearch: feeler gauge set
As an Amazon Associate we earn from qualifying purchases.