Check - Timing: BOSCH injection pump
- Make
- Citroën
- Model
- Xsara Factory Workshop Manual
- Year
- 1997–2000
- Section
- Air and fuel supply › Check - Timing: BOSCH injection pump
Check - Timing: BOSCH injection pump
1. Recommended tools
[1] flywheel setting rod 7014-T.J.
[2] bolts H M8 (-).0188 E (kit C.0188).
[3] Injection pump setting pin Ø 6 (-).0188 H (kit C.0188).
[4] dial gauge 3089-T (kit 4123-T).
[5] dial gauge support 7010-T (kit 4123-T).
[6] dial gauge extension 5003-TD (kit 4123-T).
2. Removing
Disconnect the battery negative terminal.
Raise and support the right-hand front of the vehicle.
Remove the front right-hand lower splash shield.
Unclip and move the cooling pipe away.
Remove the style cover.
Uncouple and close:
- The fuel supply pipe (4)
- The fuel return pipe (5)
Place the engine in a sling Using a workshop crane.
Remove:
- The bolts (1)
- The cross beam (2)
- The bolts (3)
- The nuts (7) and (8)
- The bracket (6)
Engage the 5th gear to allow the engine to be turned.
Remove:
- The screws (9), (10), (12), (13) and (15)
- The top cover (11)
- The intermediate cover (14)
CAUTION: Refit the screw (9) equipped with a washer (thickness 5 mm).
Disconnect the 2 connectors (16).
Remove:
- Injection pipes (18) from cylinders no.1 and no.2
- The timing opening cap (17)
Fit the dial gauge [4] with the finger [6].
Fit the dial gauge on the bracket [5].
Position the assembly in the setting hole (17).
Turn the right hand front wheel to rotate the engine in the normal direction of rotation.
Bring the camshaft and injection pump pulleys close to their setting point.
Position the flywheel setting rod [1] (from underneath the vehicle).
Turn the engine until the rod [1] engages in the flywheel.
Peg:
- The camshaft hub Using tool [2]
- The injection pump hub Using tool [3]
In this position the dial gauge should indicate the value 0,58 ± 0,04 mm.
2.1. Setting of camshaft rods impossible
Set the timing again (see the relevant operation).
2.2. Setting of camshaft rods possible but not setting of the injection pump
Perform the following operations:
- Unscrew the injection pump hub bolts
- Rotate the injection pump hub
- Insert the peg [3] into the hole
In this position the dial gauge should indicate the value 0,58 ± 0,04 mm.
ESSENTIAL: If it is impossible to obtain the value despite correct pegging, have the injection pump checked by the manufacturer’s network.
Retighten the screws of the injection pump hub.
3. Refitting
Remove tools [1], [2], [3], [4], [5]and [6].
Remove the screw (9) and the washer.
Refit:
- The top cover (11)
- The intermediate cover (14)
- The screws (15), (13), (12), (10) and (9)
- The bracket (6)
- The bolts (3) Tighten to 4,5 daN.m
- The nut (7) Tighten to 4,5 daN.m
- The nut (8) Tighten to 2,2 daN.m
- The cross beam (2)
- The bolts (1) Tighten to 2,2 daN.m
- The timing opening cap (17) (equipped with a new seal). Tighten to 1,5 daN.m
- Injection pipes (18) from cylinders no.1 and no.2
Withdraw the workshop lift.
Re-connect the connectors (16).
Remove the plug and connect:
- The fuel supply pipe (4)
- The fuel return pipe (5)
Position the styling cover.
Reposition the coolant hose and clip it in.
Refit:
- The right-hand lower mud shield
- The vehicle to its wheels
Disengage 5th gear.
Reconnect the battery negative terminal.
Parts & tools for this job For 1997 Citroën Xsara
- PARTGlow plugsSearch: Citroën Xsara 1997 glow plugs
- TOOLGlow plug socketSearch: glow plug socket
- TOOLDiesel compression testerSearch: diesel compression tester
As an Amazon Associate we earn from qualifying purchases.