21. Replace the rectifier bridge if each reading is the same.
22. Test the remaining two diodes after the above procedure.

NOTE:  Some kinds of digital ohmmeters are not suited for testing the bridge diode. In this case, consult the manufacturer regarding the test
capacity.

23. Test the diodes by connecting the ohmmeter terminals to the bridge terminal and the base plate. If the reading is the same, the rectifier bridge

should be replaced.

24. Remove the ring in the slip ring end frame.

Assembly Procedure