IS 250C V6-2.5L (4GR-FSE) (2011)
(c) Connect the 2 wire harness connectors (B) and (C) to the power steering link assembly.
(d) Install the 2 wire harness clamps to the power steering link assembly.
(e) Connect the earth wire to the bracket with the bolt (A).
Torque : 13 Nm (127 kgf-cm, 9 ft-lbf)
(f) Install the power steering earth wire to the power steering gear assembly with the bolt (E).
Torque : 5.0 Nm (51 kgf-cm, 44 in-lbf)
2. CONNECT TIE ROD END LH
(a) Connect the tie rod end LH to the front lower ball joint with the nut.
Torque : 65 Nm (663 kgf-cm, 48 ft-lbf)
(b) Install a new clip.
NOTICE:
If the holes for the clip are not aligned, tighten the nut up to 60° further.
3. CONNECT TIE ROD END RH
HINT
Perform the same procedure as for the LH side.
4. CONNECT STEERING SLIDING YOKE SUB-ASSEMBLY
(a) Align the matchmarks on the steering sliding yoke sub-assembly and the power steering link assembly.
Text in Illustration
(b) Install the bolt (A) and tighten the 2 bolts.