Installing
- Make
- Volkswagen
- Model
- Passat B5
- Year
- 1996–2005
- Section
- Removing and installing gearbox › Installing
Installing
Clean ATF cooler and ATF lines before installing an exchange gearbox → Chapter.
Always replace O rings (1).

Moisten new O-rings with ATF and insert.
Ensure that O-rings are seated correctly so that they do not slip when ATF lines are inserted.
Insert ATF lines completely to stop in gearbox by hand.
Do not tighten bolt (2) until all the ATF lines have been connected Item.
Before installing gearbox, ensure that torque converter seats correctly in gearbox → Chapter.
Before installing, ensure that dowel sleeves are correctly located.
Set up gearbox support 3282.

Set up gearbox support 3282 for automatic gearbox 01V with adjusting plate 3282/19.
The symbols on the adjusting plate indicate the mounts required; the arrow points forward.
Place gearbox on gearbox jack.
Secure gearbox to gearbox support 3282 using bolt (A).

Place gearbox jack under vehicle.
Guide gearbox in between lowered subframe and underbody.
Align gearbox to engine.
Before installing gearbox, check whether strut (B) is still pivoted to side in (direction of arrow). The strut is pivoted downwards after the gearbox has been installed.

Screw in one engine/gearbox connecting bolt hand-tight on each side.
Bolt torque converter and drive plate together.
To do this, screw in the bolts by hand and tighten to 85 Nm.

Additionally bolt on a bracket or an earth connection at many connecting bolts → Chapter.
Screw in upper engine/gearbox connecting bolts and tighten to specified torque → Chapter.

Screw the bolt of the turbocharger/gearbox strut tightly 6-cylinder diesel engine, mechanicsRep. Gr.10Installing and removing engine; Tightening torques.
Now step onto step ladder VAS 5085 to lift the engine/gearbox unit using the spindles.
Lift up the engine/gearbox unit by turning the spindles through approx. 8 turns.

When doing this, lift the engine/gearbox unit on the spindles, working alternately 2 turns at a time.
At the same time, lift the engine/gearbox unit using engine and gearbox jack V.A.G 1383 A (2nd mechanic).
Install subframe using bolts originally removed. These bolts must be replaced following wheel alignment.
Tighten the old bolts only to specified torque Running gear, axles, steering - front and four-wheel driveRep. Gr.40Repairing front suspension; Removing and installing subframe.
Warning The vehicle must not be driven in this state.
Install subframe with new bolts, observing the tightening sequence Running gear, axles, steering - front and four-wheel driveRep. Gr.40Repairing front suspension; Removing and installing subframe.
Bolt engine bearings onto subframe according to markings made for threaded connections (1) and locating sleeves (2).

Screw on nuts (1) below on left and right engine mountings Running gear, axles, steering - front and four-wheel driveRep. Gr.40Repairing front suspension; Removing and installing subframe.

Connect vacuum lines to engine mountings.
Screw in new gearbox mounting/subframe bolts (2)Chapter.
After subframe has been bolted to body, and engine/gearbox unit to subframe, remove bolt (A).

Remove engine and gearbox jack V.A.G 1383 A.
Apply anti-corrosion agent to point of contact between bolt (A) and oil pan.
Screw in engine/gearbox connecting bolts at the sides and the bottom and tighten to specified torque → Chapter.
Fit the retaining clip for the coupling rod of vehicle level sender G78 to front left track control link Running gear, axles, steering - front and four-wheel driveRep. Gr.40Electrical and electronic components and their locations; Vehicle level sender G78 on the front axle.
Do not bend or kink selector lever cable. Grease cable eye and ball socket with polycarbonate grease G 052 142 A2 before installing.
Move selector shaft lever (2) on gearbox in (direction of arrow) to position “2” and carefully use a pair of pliers to press the ball head of selector lever cable (1) onto the lever of the selector shaft.

Take care not to bend selector shaft lever (2), because otherwise it will not be possible to precisely adjust selector mechanism.
Press selector lever cable (1) fully forwards (arrow) to engage selector shaft lever (2) in position “2”.
Bolt support bracket of selector lever cable to gearbox (arrows) at marked location → Chapter.

Install selector lever cable guard plate (A) and tighten bolts (1) and (4)Chapter.

Install starter Electrical systemRep. Gr.27Starter; Removing and installing starter.
Fit ATF lines (1) to engine/gearbox unit and screw tight Item.

Screw the bracket for the ATF line onto the engine oil sump Item.

Plug connector into multi-function switch (2).

Fit connector for gearbox wiring harness and secure with locking lever (3).
Install noise insulation bracket (1)General body repairs, exteriorRep. Gr.50Body front; Assembly overview - noise insulation.
Replace cable tie (4).
Push the plug onto speedometer sender G22(arrow A).

Screw engine speed sender G28(arrow B) onto gearbox.
Install drive shafts (1) onto flange shafts Running gear, axles, steering - front and four-wheel driveRep. Gr.40Repairing drive shafts; Removing and installing drive shafts.

Install left drive shaft guard plate (arrows). Third bolt cannot be seen in figure Running gear, axles, steering - front and four-wheel driveRep. Gr.40Repairing drive shafts; Removing and installing drive shafts.
Install front exhaust system with catalytic converter6-cylinder diesel engine, mechanicsRep. Gr.26Removing and installing parts of the exhaust system.
Fit left and right drive shaft noise insulation to wheel housing.

Install noise insulation elements (arrows).

In vehicles with an auxiliary heater, screw the exhaust pipe firmly onto the noise insulation.
Install front wheels Running gear, axles, steering - front and four-wheel driveRep. Gr.44Torque settings for wheel bolts.
Remove support device 10-222A.
Screw on the securing nuts for the exhaust pipe on the turbocharger manifold 6-cylinder diesel engine, mechanicsRep. Gr.26Removing and installing parts of the exhaust system.

Install the heat shield above the turbocharger (arrows)6-cylinder diesel engine, mechanicsRep. Gr.26Installing and removing parts of exhaust system.

Fit the intake hose onto the induction manifold.
Put on the engine cover and tighten the nuts 6-cylinder diesel engine, mechanicsRep. Gr.10Installing and removing engine; Tightening torques.

Clip in covers for the nuts.
Connect the battery earth strap Electrical systemRep. Gr.27Battery; Disconnecting and connecting battery.
Initialise electric windows and set clock MaintenanceBooklet36.
Code radio Radio, telephone, navigationRep. Gr.91Radio, telephone, navigation.
Check selector lever cable adjustment and adjust if necessary → Chapter.
With gearbox installed, check gear oil level in final drive → Chapter.
Finally, check ATF level and top up → Chapter.
When checking ATF level, check ATF line connections (A) and (B) for leaks.

Check connections (1) of the ATF lines for leaks when checking ATF level.

There is no need to take account of bolts (2) and (3) in this case.
Parts & tools for this job For 1996 Volkswagen Passat
- PARTTransmission filter kitSearch: Volkswagen Passat 1996 transmission filter kit
- FLUIDAutomatic transmission fluidSearch: Volkswagen automatic transmission fluid
- TOOLFluid transfer pumpSearch: fluid transfer pump
As an Amazon Associate we earn from qualifying purchases.