PINPOINT TEST A : THE DAYTIME RUNNING LAMPS ARE INOPERATIVE |
TEST CONDITIONS | DETAILS/RESULTS/ACTIONS |
A1: CHECK FUSE F48 (5 A) (SRB) |
NOTE:Headlamp switch in OFF position. |
| 1 Ignition switch in position 0. |
| 2 Disconnect CHECK fuse F48 (5 A) (SRB). |
| 3 CHECK CHECK fuse F48 (5 A) (SRB). |
| Is the fuse OK? Yes No RENEW fuse F48 (5 A) (SRB) CHECK system operates correctly If fuse blows again, LOCATE and REMEDY the short to ground using the Wiring Diagrams. CHECK system operates correctly |
A2: CHECK THE VOLTAGE SUPPLY TO FUSE F48 (5 A) (SRB) FOR OPEN CIRCUIT |
| 1 Connect CHECK fuse F48 (5 A) (SRB). |
| 2 Ignition switch in position II. |
| 3 Measure the voltage between fuse F48 (5 A) (SRB) and ground. |
| Does the meter display battery voltage? Yes No LOCATE AND RECTIFY the break in the voltage supply of fuse F48 (5A) (SRB) using the Wiring Diagrams. CHECK system operates correctly |
A3: CHECK FUSE F54 (30 A) (SRB) |
| 1 Ignition switch in position 0. |
| 2 Disconnect CHECK fuse F54 (30 A) (SRB). |
| 3 CHECK CHECK fuse F54 (30 A) (SRB). |
| Is the fuse OK? Yes No RENEW fuse F54 (30 A) (SRB) CHECK system operates correctly If fuse blows again, LOCATE and RECTIFY the short to ground using the Wiring Diagrams. CHECK system operates correctly |
A4: CHECK THE VOLTAGE SUPPLY TO FUSE F54 (30 A) (SRB) FOR OPEN CIRCUIT |
| 1 Connect CHECK fuse F54 (30 A) (SRB). |
| 2 Ignition switch in position II. |
| 3 Measure the voltage between fuse F54 (30 A) (SRB) and ground. |
| Does the meter display battery voltage? Yes No LOCATE AND RECTIFY the break in the voltage supply of fuse F54 (30 A) (SRB) using the Wiring Diagrams. CHECK system operates correctly |
A5: RULE OUT CENTRAL JUNCTION BOX (CJB) AS THE CAUSE OF THE FAULT |
| 1 Ignition switch in position 0. |
| 2 Disconnect Central junction box (CJB) from connector CBP02D. |
| 3 Connected a fused jumper wire (5 A) to the central junction box (CJB), connector CBP02D, between pin 12, circuit CLF10A (GN/OG), wiring harness side and ground. |
| 4 Ignition switch in position II. |
| 5 Check the daytime running lamps. |
| Are the daytime running lamps lit up? Yes INSTALL a new CJB. CHECK system operates correctly No |
A6: CHECK THE CONTROL CIRCUIT OF THE THE DAYTIME RUNNING LAMPS RELAY FOR OPEN CIRCUIT |
| 1 Ignition switch in position 0. |
| 2 Disconnect Standard relay box (SRB) from connector CB101B. |
| 3 Measure the resistance between the central junction box (CJB), connector CBP02D, pin 12, circuit CLF10A (GN/OG), wiring harness side and standard relay box (SRB), connector CB101B, pin 10, circuit CLF10A (GN/OG), wiring harness side. |
| Is a resistance of less than 2 ohms registered? Yes RENEW standard relay box (SRB). CHECK system operates correctly No LOCATE and RECTIFY break in circuit between central junction box (CJB) and standard relay box (SRB). CHECK system operates correctly |