01 Technical data for engines02 6-cylinder direct petrol injection engine (3.2 ltr. 4-valve)03 Fuel supply system, petrol engines04 4-cylinder TDI engine (2.0 ltr. 4-valve common rail)05 6-cylinder TDI engine (3.0 ltr. 4-valve common rail)06 4-cylinder direct injection engine (2.0 ltr. 4-valve TFSI - generation II)07 Fuel supply system, diesel engines08 4-cylinder TDI engine (2.0 ltr. 4-valve common rail - generation II)09 6-cylinder direct injection engine with supercharger (3.0 ltr. 4-valve TFSI)10 6-cylinder TDI engine (3.0 ltr. 4-valve common rail - generation II)11 4-cylinder direct injection engine (1.8, 2.0 ltr. 4-valve TFSI - generation III)12 4-cylinder TDI engine, 2.0 ltr. 4-valve common rail (EA 288 Gen. I)13 6-speed manual gearbox 0B2, four-wheel drive14 Rear final drive 0BC, 0BD, 0BE, 0BF15 Servicing 6-speed manual gearbox 0B2, four-wheel drive16 Servicing 6-speed manual gearbox 0B1, front-wheel drive17 Servicing 7-speed dual clutch gearbox 0B5 (S tronic)18 6-speed manual gearbox 0B1, front-wheel drive19 7-speed dual clutch gearbox 0B5 (S tronic)20 8-speed automatic gearbox 0BK, four-wheel drive21 8-speed automatic gearbox 0BW hybrid, four-wheel drive22 Automatic gearbox 0B6, four-wheel drive23 Running gear: Specifications for testing the braking force (according to German legislation)24 Running gear: Trailer Operation Guide25 Running gear, front-wheel drive and four-wheel drive26 Brake system27 System description - dynamic steering28 System description - steering wheel29 Running gear: Wheel/Tyre Guide30 Heating, air conditioning31 Heating and air conditioning: Auxiliary heater, supplementary heater32 System description - interior lights33 Electrical: System description - exterior lights34 System description - wiper and washer systems35 Electrical: System description - entry and start authorisation36 Electrical: Basic information on high-voltage vehicles37 Electrical: System description - infotainment and navigation system38 Electrical: System description - adaptive cruise control39 System description - infotainment and audio output (MOST)40 Electrical system41 Electrical system, hybrid42 Electrical: Communication43 General body repairs, exterior44 System description - Windows and doors45 General body repairs, interior
Audi Q5 Mk1 (2008-2017)22 · Automatic gearbox 0B6, four-wheel drive
22 · Transmission

Procedure

Make
Audi
Model
Q5 Mk1
Year
2008–2017
Section
Gearbox control system › Procedure
Automatic gearbox 0B6, four-wheel driveProcedure

Procedure

Note

  • Mask the roof side members with adhesive tape to protect them from damage and dirt.
  • Take care not to damage the front and rear roof cross members when cutting out.

Cutting locations

Roughly cut out roof parallel with plasmatron weld seam (1) at a distance of approx. 30 mm using body saw.

Drill off original joint to windscreen opening and rear lid opening using spot weld breaker.

Working from passenger compartment, separate bonded joints between roof and roof cross members using electric cutter V.A.G 1561A.

A51-10501

Note

  • Take care not to damage the roof side members when making cuts and when moving the remaining sections of the roof up and down.

Make cuts in remaining sections of roof using tin snips VAS 5357.

Grip remaining sections with pliers and break open plasmatron weld seam by moving up and down.

A51-10502

Note

  • Take care not to damage the roof side members (1) when removing the remaining sections of the roof (2).
  • Use a suitable flap disc; do not use a cutting disc or rough-filing disc.

Remove remaining sections (2) using compact angle grinder.

Grind bonding areas down to bare metal.

A51-10503

Replacement parts

  • Roof
  • Retaining bracket, 10x
  • Bolt with washer M8x16, 20x
  • Single-component assembly adhesive D 190 MKD A3, 1 cartridge
  • 2-component epoxy adhesive DA 180 A00 A2, 1 set of cartridges
  • Silicone remover LSE 020 100 A3
  • Zinc spray

Preparing new part

Note

  • It is essential to observe the following sequence of operations to ensure satisfactory and effective roof repair.
  • Bonded areas must not be treated with filler coat (surfacer) and painted before bonding in the roof.
  • The adhesive materials must be applied very quickly.
  • Make sure adhesive is applied before pot life is exceeded.
  • Use a pneumatic cartridge gun to apply the bonding materials.
  • Affixing adhesive tape to the roof parallel with the bonded seam on the side prevents soiling when bonding.

Note

  • The retaining brackets can be moved by ± 15 mm in the longitudinal direction. This is intended to avoid drilling through any spot welds on the roof frame. Drilling through spot welds would reduce the strength of the body.

Position retaining brackets on roof frame according to dimensions (a), (b) and (c) and slide right up against side panel.

Fix retaining brackets in position.

Mark drill holes. Then detach retaining brackets and centre punch drill holes.

Using drill, drill 10 mm ∅ holes from above in roof frame.

Deburr drill holes.

Dimension (a) = 53 mm

Dimension (b) = 4 mm

Dimension (b) = 112 mm

A51-10504

Bonding in

Position roof on roof frame and check alignment of roof with roof side members (visual inspection).

Check fit of roof with rear lid and windscreen.

Fix roof in position in windscreen flange and sealing flange of rear lid using one self-tapping screw at each end.

A51-10505

Mark position of retaining brackets on inside of roof.

A51-10506

Remove roof.

Grind marked positions of retaining brackets on roof down to bare metal.

Grind bonding areas on both sides of roof down to bare metal.

Grind outside of welding flanges at windscreen opening and rear lid opening down to bare metal.

This ensures that the 2-component epoxy adhesive DA 180 A00 A2 forms a good joint with the bonding area.

A51-10507

Mask outside of roof panel parallel with side bonding area using adhesive tape.

Attach four suction lifters V.A.G 1344 or magnets VAS 6739 to outside of roof panel.

Clean roof frame, retaining brackets and roof with silicone remover LSE 020 100 A3.

Treat welding flanges for RP spot weld seam at roof cross members (1) and on roof (1) with zinc spray.

A51-10508

Cut off approx. 2 mm from nozzle (B) to obtain appropriate bead geometry.

N51-10238

Apply single component assembly adhesive D190 MKD A3 with pneumatic cartridge gun V.A.G 1761/1 to roof cross member at front and rear in vicinity of factory bonding location.

A51-10509

Cut static mixer from 2-component epoxy adhesive DA 180 A00 A2 down to 4th notch to obtain required bead cross-section.

N51-1230

Note

  • The pot life of the 2-component epoxy adhesive DA 180 A00 A2 is roughly 90 minutes.
  • A second mechanic is required for the next steps.

Operate the pneumatic gun VAS 6453 with the 2-component epoxy adhesive DA 180 A00 A2 and apply a roughly 100 mm long adhesive bead to a piece of cardboard before starting application on the vehicle.

Apply continuous bead (1) of 2-component epoxy adhesive DA 180 A00 A2 to bevelled sections of roof side members using pneumatic gun VAS 6453.

Apply 2-component epoxy adhesive DA 180 A00 A2 with pneumatic gun VAS 6453 to roof frame in vicinity of retaining brackets (2).

A51-10510

Apply one continuous bead of 2-component epoxy adhesive DA 180 A00 A2 to side flanges of roof (1) using pneumatic gun VAS 6453.

Apply 2-component epoxy adhesive DA 180 A00 A2 using pneumatic gun VAS 6453 to marked contact surfaces of retaining brackets on inside of roof.

A51-10511

Immediately fit and align roof.

Use one self-tapping screw at each end to fix roof in position in centring hole in windscreen flange and sealing flange for rear lid.

Fix roof in position at windscreen opening and rear lid opening using mole grips, 18-18 VAS 5430/1.

Note

  • The roof must be bolted on evenly on the right and left, working from the centre to the front and rear to avoid straining the roof on installation.

Apply 2-component epoxy adhesive DA 180 A00 A2 using pneumatic gun VAS 6453 to clamping flanges of retaining brackets.

Position retaining brackets on roof frames and bolt on in specified sequence.

A51-10512

Roughly spread any 2-component epoxy adhesive DA 180 A00 A2 that comes out at the edge of the roof.

Note

  • After bonding, the vehicle must be left standing on a level surface for 8 ...10 hours at room temperature (min. 15 °C) so that the adhesive components can harden (curing time).
  • Do not perform any further work on the vehicle until the “curing time” has elapsed.

Welding in

Note

  • Due to the different types of steel and panel thicknesses employed, one of the resistance spot welding units listed in this manual and approved by Audi must be used to ensure correct results when spot welding.

Weld in roof using resistance spot welder: RP spot weld seam.

A51-10513

Make additional welds for roof using shielded arc welding equipment: SG continuous seam.

Grind down SG continuous weld seams using compact angle grinder.

A51-10514

Grind zero-gap joint (1) into shape (left and right).

A51-10515

Parts & tools for this job For 2008 Audi Q5