Re-pressurising: CNG supply circuit
- Make
- Citroën
- Model
- Saxo Factory Workshop Manual
- Year
- 1996–2004
- Section
- Air and fuel supply › Re-pressurising: CNG supply circuit
Re-pressurising: CNG supply circuit
CAUTION: A gas leak may occur in the natural gas supply circuit at low pressure and disappear at high pressure and vice versa.
ESSENTIAL: Never re-tighten or unscrew connectors under pressure.
N.B.: Before refitting CNG components, make sure that no impurities have penetrated inside the piping or into the threads of the unions.
1. Recommended tools
[1] leak detector FRAMET DF9.
2. Re-pressurising
Close the natural gas supply circuit again and re-tighten the connectors (see the relevant operation).
N.B.: The manual safety valve located at "a" on the CNG tank should be closed.
2.1. Achieving a defined pressure
To achieve a defined pressure in the high pressure supply circuit (in the CNG tank at the CNG pressure reducer), proceed as follows:
N.B.: Checking is done by using a "shunt" (2), placed between the CNG pressure sensor (1) and its connector (3). The output signal is registered using a multimeter on the terminal "b".
Open the manual safety valve on the CNG tank.
Run the engine in natural gas mode.
Close the manual safety valve, then inspect the voltage on the multimeter to obtain the pressure.
The table indicates the relation between the pressure and the output voltage (50 bars = 1 volt).
2.2. Stage 1
Spray the unions already dismantled, with tool [1] (failing that, use soapy water).
Open then rapidly reclose the manual safety valve at "a" on the CNG tank to obtain a partial pressure in the CNG circuit.
Run the engine in natural gas mode until it changes to petrol mode.
Stop the engine.
Check for any leaks at the CNG unions (presence of bubbles) using tool [1], or soapy water.
ESSENTIAL: Should there be a leak of gas at the union, carry out a partial draining of the CNG system, Retighten the union, then restart the operations to re-pressurise the CNG supply circuit.
CAUTION: Wait a few minutes, then perform a new check Using tool [1].
2.3. Stage 2
Spray the unions already dismantled, with tool [1] (failing that, use soapy water).
Open then rapidly reclose the manual safety valve at "a" on the CNG tank to obtain a partial pressure in the CNG circuit.
Run the engine in CNG mode until the pressure reaches around 50 bars (± 10 bar). (see operation: achieving a defined pressure).
Stop the engine.
Check for any leaks at the CNG unions (presence of bubbles) using tool [1], or soapy water.
ESSENTIAL: Should there be a leak of gas at the union, carry out a partial draining of the CNG system Retighten the union, then restart the operations to re-pressurise the CNG supply circuit.
CAUTION: Wait a few minutes, then perform a new check Using tool [1].
2.4. Stage 3
Open the manual safety valve at "a" on the CNG tank.
Run the engine in CNG mode until the pressure reaches around 100 bars (see operation: achieving a defined pressure).
Stop the engine.
Check for any leaks at the CNG unions (presence of bubbles) using tool [1], or soapy water.
ESSENTIAL: Should there be a leak of gas at the union, carry out a partial draining of the CNG system Retighten the union, then restart the operations to re-pressurise the CNG supply circuit.
CAUTION: Wait a few minutes, then perform a new check Using tool [1].
2.5. Stage 4
N.B.: This stage should be performed at a pressure of 200 bars, the CNG tank should therefore be filled to maximum capacity. If this is not the case, top up at the closest natural gas station.
Open the manual safety valve at "a" on the CNG tank.
Run the engine in natural gas mode.
Check for any leaks at the CNG unions (presence of bubbles) using tool [1], or soapy water.
ESSENTIAL: Should there be a leak of gas at the union, carry out a partial draining of the CNG system Retighten the union, then restart the operations to re-pressurise the CNG supply circuit.
After an idle phase of at least 3 hours, carry out a final detection of leaks before supplying to the customer.
3. Additional operations
To prevent all risks of corrosion after using a leak detector:
- Rinse the unions with clean water
- Dry the unions with compressed air
Parts & tools for this job For 1996 Citroën Saxo
- TOOLDigital multimeterSearch: automotive digital multimeter
- PARTAssorted fuse kitSearch: car fuse assortment kit
- TOOLWire crimper and connector kitSearch: wire crimper connector kit
As an Amazon Associate we earn from qualifying purchases.