01 Engine02 Gearbox and clutch03 Transmission and driveshafts04 Suspension05 Steering06 Brakes07 Body - front section08 Body - rear section09 Body - side structure10 Front doors and trim11 Rear doors and trim12 Body - roof and headlining13 Body shell14 Lighting and signalling15 Wipers and washers16 Fascia and interior panels17 Front seats18 Electrical - general19 Starting and charging20 Locking, alarm and airbags21 Heating, air conditioning and audio
Citroën Jumper II Factory Workshop Manual (2002-2006)01 · Engine
01 · Engine

Removing - refitting: Engine/gearbox assembly (DW12UTED)

Make
Citroën
Model
Jumper II Factory Workshop Manual
Year
2002–2006
Section
Engine assembly › Removing - refitting: Engine/gearbox assembly (DW12UTED)
EngineRemoving - refitting: Engine/gearbox assembly (DW12UTED)

Removing - refitting: Engine/gearbox assembly (DW12UTED)

Citroën Jumper II · Removal-fitting · Ref. B1BG55P0

Applies to: 2.2 HDi (DW12UTED) from date 01/00/1700

1. Recommended tools

Figure b1bp030c
ReferenceDesignationReferenceReference
[1][/] bonnet securing catch5706-T(-).1331
Figure e5-p12cc
ReferenceDesignationReferenceReference
[2][/] hub immobilising tool6310-T(-).0606 AY
Figure e5-p07jc
ReferenceDesignationReferenceReference
[3][] pliers for removing the plastic pegs7504-T(-).1311
Figure e5ap1gvc
ReferenceDesignationReferenceReference
[4a][] engine support with reversible tool5704-T(-).0005
[4b][/] engine supports5704-T(-).0005
Figure e5ap1gwc
ReferenceDesignationReferenceReference
[5][/] lifting bench5702-T.A(-).0004
Figure e5ap17wc

[6] plugs kit.

ReferenceDesignationReferenceReference
[6][/] plugs kit(-).0188 T(-).0188 T

2. Removing

ESSENTIAL: Respect the safety and cleanliness recommendations that are specific to high pressure diesel injection (HDi) engines.

Disconnect the battery negative terminal.

Lift and support the vehicle.

Figure b1bp035c

Set the bonnet vertically by means of tool [1].

Drain:

  • The cooling system (see the relevant operation)
  • The gearbox
  • Power assisted steering reservoir

Remove:

  • The front wheels
  • The protection plates under the engine
Figure c4ap16wd

Remove:

  • The bolts (1)
  • The grille
Figure c4ap16xc

Remove the front mud shields (2) Using tool [3].

Figure c4ap16yc

Remove tie-rods (3) from the bumper.

Figure c4ap16zc

Remove the 2 bolts (4).

Figure c4ap170c

Remove:

  • The nut (5)
  • The (6) bolt

Disengage the ball-joint at "a" and remove the LH headlamp.

Do the same for the RH headlamp.

Figure c4ap178d

Disconnect the connector of the flowmeter.

Remove:

  • The air filter assembly (11), The air flow meter and air inlet duct (10)
  • The air ducts (8)
  • The cover (9)
  • The support (17) with the power steering fluid reservoir (18)
  • The expansion bottle (7)
  • Bonnet locking (13)

Uncouple:

  • The upper and lower hoses of the cooling radiator
  • The venting hoses on the cylinder head

Disconnect the electric harnesses.

Uncouple the cooling fan connectors.

Remove:

  • The bolts (12)
  • The bolts (14)
  • The air/air heat exchanger fixing on the front panel (15)
  • The cooling radiator fixings on the front panel (15)
  • The front panel with the bumper (16)
Figure c4ap179c

Remove:

  • The bolts (19) (on the L.H. and RH sides)
  • The cross beam (20)
Figure c5hp194d

2.1. Vehicle without air conditioning

Remove:

  • The fixings from the abs hydraulic block
  • The cooling radiator (22)
  • Air/air heat exchanger (21)
  • The bolts (24) (on the L.H. and RH sides)
  • The lower crossmember (25)

2.2. Vehicle with air conditioning

Protect the cooling condenser (26) with cardboard.

Remove the bolts (23).

Carefully release the air conditioning condenser from the body.

Remove:

  • The fixings from the electric harnesses on the fan unit
  • The cooling radiator (22)
  • Air/air heat exchanger
  • The fixings from the abs hydraulic block (according to equipment)
  • The bolts (24) (on the L.H. and RH sides)
  • The lower crossmember (25)
  • The accessories drive belt (see the relevant operation)
  • The air conditioning compressor fixings

Suspend the air conditioning compressor on the left hand side of the vehicle.

2.3. Removing (continued)

Disconnect:

  • The starter electrical supply
  • The reversing lamp connector
  • The ABS connectors (according to equipment)

Detach and move aside:

  • The fuel feed and return pipes
  • The clutch slave cylinder
  • The earth cable
  • The braking assistance pipe (on the brake servo)

Remove the fixing of the link tube between the power steering pump and the rotary valve.

Uncouple and blank the link tube between the power steering pump and the rotary valve Using tool [6].

Remove the drive shafts Using tool [2] (see the relevant operation).

Uncouple:

  • The gearchange ball-joints
  • All the gear controls on the gearbox

Unplug:

  • The speedometer cable
  • The alternator electrical harness
  • The heater matrix inlet and outlet hoses
  • The oil pressure switch
Figure b2cp3jpc

Remove:

  • The reaction link (28)
  • The bolts (27)
Figure b1bp2jfc

Put support [4a] into place in the RH driveshaft bearing.

Figure e5ap1gxc

Put lifting table [5] together with its supports [4b] in position under the engine.

Lift the elevating platform [5].

Clamp the engine-gearbox assembly using tools [4a] and [4b].

Figure b1bp2qfd

Remove:

  • The 3 bolts (29)
  • The 4 bolts (30)
  • The power unit assembly (via the front of the vehicle)

3. Refitting

Place the power unit on the lifting table [5].

Refit:

  • The power unit assembly (via the front of the vehicle)
  • The 4 bolts (30) Tighten to 8 ± 0,8 daN.m
  • The 3 bolts (29) Tighten to 5 ± 0,5 daN.m

Unclamp the power unit assembly from the lifting table [5].

Remove the tool [4a].

Withdraw the lifting bench [5] from under the vehicle.

Refit:

  • The reaction link (28)
  • The bolts (27) Tighten to 1 ± 0,1 daN.m

N.B.: Gearbox end Tighten to 9 ± 0,9 daN.m. Engine sub-frame side Tighten to 5 ± 0,5 daN.m.

Reconnect:

  • The heater matrix inlet and outlet hoses
  • The alternator electrical harness
  • The oil pressure switch
  • The speedometer cable

Couple up:

  • All the gear controls on the gearbox
  • The gearchange ball-joints

Refit the drive shafts (see the relevant operation).

Remove the tool [6].

Reconnect and refix the link tube between the power steering pump and the rotary valve.

Reposition and reconnect:

  • The braking assistance pipe (on the brake servo)
  • The earth cable
  • The clutch slave cylinder
  • The fuel feed and return pipes

Reconnect:

  • The ABS connectors (according to equipment)
  • The reversing lamp connector
  • The starter electrical supply

3.1. Vehicle with air conditioning

Reposition and re-fix the air conditioning compressor.

Refit the ancillary belt (see the relevant operation).

Reconnect the electrical supply of the air conditioning compressor.

Refit:

  • The lower crossmember (25)
  • The bolts (24) (on the L.H. and RH sides)
  • The fixings from the abs hydraulic block (according to equipment)
  • Air/air heat exchanger (21)
  • The cooling radiator (22)
  • The fixings from the electric harnesses on the fan unit

Reposition the air conditioning condenser (26) and take away the protective card.

Refit the bolts (23).

3.2. Vehicle without air conditioning

Refit:

  • The lower crossmember (25)
  • The bolts (24) (on the L.H. and RH sides)
  • The fixings from the abs hydraulic block (according to equipment)
  • Air/air heat exchanger (21)
  • The cooling radiator (22)

Reconnect the connectors on the cooling fan unit.

3.3. Refitting (continued)

Reconnect the electrical harnesses.

Recouple:

  • The venting hoses on the cylinder head
  • The upper and lower hoses of the cooling radiator

Refit:

  • The cross beam (20)
  • The bolts (19) (on the L.H. and RH sides)
  • The front panel (15) and bumper (16) assembly
  • The bolts (15)
  • Bonnet locking (13)
  • The expansion bottle (7)
  • The support (17) with the power steering fluid reservoir (18)
  • The cover (9)
  • The air duct (8)
  • The air filter assembly (11), The air flow meter and air inlet duct (10)

Recouple the connector on the flow meter.

Remove:

  • The bolts (4)
  • Bumper tie-rods (3)
  • The front splash shields (2)
  • The grille
  • The bolts (1)
  • The protection plates under the engine
  • The front wheels

Fill and top up the level of the following of the following elements:

  • The gearbox
  • Power assisted steering reservoir
  • The cooling system (see the relevant operation)

Start the engine.

Operate the steering slowly from lock to lock to bleed the ram.

Top up the level if necessary.

Remove the tool [1].

Return the vehicle to its wheels.