01 Engine02 Gearbox and clutch03 Transmission and driveshafts04 Suspension05 Steering06 Brakes07 Body - front section08 Body - rear section09 Body - side structure10 Front doors and trim11 Rear doors and trim12 Body - roof and headlining13 Body shell14 Lighting and signalling15 Wipers and washers16 Fascia and interior panels17 Front seats18 Rear seats19 Interior trim20 Electrical - general21 Starting and charging22 Wiring harnesses23 Locking, alarm and airbags24 Heating, air conditioning and audio
Citroën Jumper III Factory Workshop Manual (2006-2017)01 · Engine
01 · Engine

Removing - refitting: Engine/gearbox assembly (22DT)

Make
Citroën
Model
Jumper III Factory Workshop Manual
Year
2006–2017
Section
Engine assembly › Removing - refitting: Engine/gearbox assembly (22DT)
EngineRemoving - refitting: Engine/gearbox assembly (22DT)

Removing - refitting: Engine/gearbox assembly (22DT)

Citroën Jumper III · Removal-fitting · Ref. B1BG9BP0

Applies to: 2.2 HDi 100 puma or 2.2 HDi 120 puma

1. Recommended tools

Figure e5ap32kd
ReferenceDesignationReferenceReference
[1]Bonnet retaining hook5706-T(-).1331
Figure e5ap32ld
ReferenceDesignationReferenceReference
[2a]Engine mounting with reversible tool5704-T(-).0005
[2b]engine supports5704-T(-).0005
Figure e5ap32md
ReferenceDesignationReferenceReference
[3]lifting bench5702-T.A(-).0004
Figure e5ap32nd
ReferenceDesignationReferenceReference
[4]plugs kit(-).0188 T(-).0188 T

2. Removing

ESSENTIAL: Respect the safety and cleanliness recommendations that are specific to high pressure diesel injection (HDi) engines.

CAUTION: After switching off the ignition, wait 15 minutes before disconnecting the battery (to guarantee that the initialisations of the various ECUs are memorised).

Disconnect the battery negative terminal.

Place the vehicle on a 2-post lift.

Figure b1bprwyd

Put the bonnet in the vertical position; Using tool [1].

Drain:

  • The engine cooling system (see the relevant operation)
  • The gearbox (see the relevant operation)
  • The cylinder block

Remove:

  • The front wheels
  • The protective panel under the engine
  • The protective panel under the engine Right
  • The drive shafts (see the relevant operation)
  • The pre-catalytic converter (see the relevant operation)
Figure c4ap1rcd

Uncouple:

  • The cooling radiator pipes (1)
  • The turbocharging air cooler pipes (5)
  • The heater matrix inlet and outlet hoses (3)
  • The expansion bottle pipe (2)
  • The fuel supply and return pipes (4)

Plug the fuel supply and return pipes (4); Using tool [4].

Figure b1bprwzd

Remove:

  • The braking assistance pipe (6) (Direct connection to the vacuum pump)
  • The air filter casing (7)
  • The air ducts (8)
  • The air flow meter (9)

Plug the braking assistance pipe (6); Using tool [4].

Figure d4ap08qd

Disconnect the electric harnesses (10).

Remove:

  • The auxiliary equipment drive belt (see the relevant operation)
  • The power steering pump (Without opening the cooling system) (see the relevant operation)

Move aside and suspend the power steering pump.

2.1. Vehicle with air conditioning

Figure b1gp0fcd

Remove:

  • The air conditioning compressor bolts (12)
  • The clip (11) securing the air conditioning pipes on the rear lifting plate

Move aside and suspend the air conditioning compressor on the side of the vehicle (Without opening the cooling system).

2.2. Removing (continued)

Detach and move aside:

  • The clutch slave cylinder
  • The earth cable
  • The starter electrical supply
  • The gear control cables
Figure b1bprx0d

Remove:

  • The screws (14), (15) and (16)
  • The lower torque reaction link (13)

Put support [2a] into place in the RH driveshaft bearing.

Figure e5ap32pd

Put lifting table [3] together with its supports [2b] in position under the engine.

Lift the elevating platform [3].

Clamp the engine-gearbox assembly using tools [2a] and [2b].

Figure b1bprx1d

Remove:

  • The nuts (17), (22) and (20)
  • The screws (18), (19) and (21)

Slowly lower the engine and gearbox assembly (using the lifting bench [3]).

CAUTION: Ensure that there is no fouling between the engine-gearbox assembly and the body.

Manoevre the engine-gearbox assembly to facilitate removal.

Remove the power unit assembly (from below).

Move the engine-gearbox assembly away from under the vehicle.

3. Refitting

Place the engine/gearbox assembly on the hydraulic table [3].

Refit the engine-gearbox assembly (from underneath the vehicle).

CAUTION: Ensure that there is no fouling between the engine-gearbox assembly and the body. Manoevre the engine-gearbox assembly to facilitate its repositioning.

Refit:

  • The nuts (17), (22) and (20)
  • The screws (18), (19) and (21)

Tighten:

  • The nuts (17) to 11 ± 1,2 daN.m
  • The bolts (18) to 10 ± 2,3 daN.m
  • The bolts (19) to 10 ± 3,2 daN.m
  • The nuts (20) to 11 ± 1,2 daN.m
  • The bolts (21) to 10 ± 2,7 daN.m
  • The nut (22) to 10 ± 0,3 daN.m

Unclamp the power unit assembly from the lifting table [3].

Remove the tool [2a].

Withdraw the lifting bench [3] from under the vehicle.

Refit:

  • The lower torque reaction link (13)
  • The screws (14), (15) and (16)

Tighten:

  • The bolts (14) to 15 ± 1,8 daN.m
  • The bolts (15) to 30 ± 9 daN.m
  • The bolts (16) to 33 ± 4,6 daN.m

Reposition and reconnect:

  • The gear control cables
  • The starter electrical supply
  • The earth cable
  • The clutch slave cylinder

Tighten the slave cylinder bolts to 2 ± 0,5 daNm.

3.1. Vehicle with air conditioning

Reposition and re-fix the air conditioning compressor.

Tighten the bolts (12) to 2,5 ± 0,25 daN.m.

Refit the clip (11) securing the air conditioning pipes on the lifting plate; Tighten the bolt to 1 ± 0,4 daN.m.

3.2. Refitting (continued)

Reconnect the electrical harnesses.

Refit:

  • The power steering pump (see the relevant operation)
  • The auxiliary equipment drive belt (see the relevant operation)

Refit:

  • The air flow meter (9)
  • The air ducts (8)
  • The air filter casing (7)
  • The braking assistance pipe (6) (On the vacuum pump)

Recouple:

  • The fuel supply and return pipes (4)
  • The expansion bottle pipe (2)
  • The heater matrix inlet and outlet hoses (3)
  • The turbocharging air cooler pipes (5)
  • The cooling radiator pipes (1)

Refit:

  • The pre-catalytic converter (see the relevant operation)
  • The drive shafts (see the relevant operation)
  • The protective panel under the engine
  • The protective panel under the engine Right

Fill and top up the level of the following of the following elements:

  • The engine
  • The gearbox (see the relevant operation)
  • The cooling system (see the relevant operation)

Reconnect the battery negative terminal.

Start the engine.

Top up the level if necessary.

Remove the tool [1].

Return the vehicle to its wheels.