01 Engine02 Gearbox and clutch03 Transmission and driveshafts04 Suspension05 Steering06 Brakes07 Body - front section08 Body - rear section09 Body - side structure10 Front doors and trim11 Rear doors and trim12 Body - roof and headlining13 Body shell14 Lighting and signalling15 Wipers and washers16 Fascia and interior panels17 Front seats18 Rear seats19 Interior trim20 Electrical - general21 Starting and charging22 Wiring harnesses23 Locking, alarm and airbags24 Heating, air conditioning and audio
Citroën Jumper III Factory Workshop Manual (2006-2017)01 · Engine
01 · Engine

Removing - refitting: Engine/gearbox assembly (30DT)

Make
Citroën
Model
Jumper III Factory Workshop Manual
Year
2006–2017
Section
Engine assembly › Removing - refitting: Engine/gearbox assembly (30DT)
EngineRemoving - refitting: Engine/gearbox assembly (30DT)

Removing - refitting: Engine/gearbox assembly (30DT)

Citroën Jumper III · Removal-fitting · Ref. B1BG0103P0

Applies to: 3.0 HDi 160 PEF or 3.0 HDi 160 PEF euro 5 or 3.0 HDi 145 PEF euro 5 or 3.0 HDi 160

ESSENTIAL: Observe the safety and cleanliness recommendations.

1. Tooling

Figure e5ap32kd
ReferenceDesignationReferenceReference
[1]Bonnet retaining hook5706-T(-).1331
Figure e5ap32ld
ReferenceDesignationReferenceReference
[2a]Engine mounting with reversible tool5704-T(-).0005
[2b]engine supports5704-T(-).0005
Figure e5ap32md
ReferenceDesignationReferenceReference
[3]lifting bench5702-T.A(-).0004
Figure e5ap32nd
ReferenceDesignationReferenceReference
[4]plugs kit(-).0188 T(-).0188 T

2. Removing

ESSENTIAL: Respect the safety and cleanliness recommendations that are specific to high pressure diesel injection (HDi) engines.

CAUTION: After switching off the ignition: wait 15 minutes before disconnecting the battery, to ensure that the initialisations of the various ECUs are memorised.

Disconnect the battery.

Place the vehicle on a 2-post lift.

Figure b1bprwyd

Put the bonnet in the vertical position; Using tool [1].

Drain:

  • The engine cooling system   (see the relevant operation)
  • The gearbox   (see the relevant operation)

Remove:

  • The central section of the lower front panel   (see the relevant operation)
  • The right-hand headlamp   (see the relevant operation)
  • The front wheels
  • The protective panel under the engine
  • The drive shafts   (see the relevant operation)
  • The pre-catalytic converter   (see the relevant operation)

Uncouple:

  • The cooling radiator pipes
  • The turbocharger air cooler pipe   (right hand side)
  • The heater matrix inlet and outlet hoses
  • The expansion bottle pipe
  • The fuel supply and return pipes

Plug the fuel supply and return pipes; Using tool [4].

Figure b1bm001d

Disconnect the air flow meter.

Remove:

  • The braking assistance pipe (1)
  • The electrical harness shield (2)
  • The cover (3)
  • The air filter housing (4)
  • The air duct (5)

Plug the braking assistance pipe; Using tool [4].

Figure d4am001d

Disconnect the electric harnesses (6).

2.1. Vehicle with air conditioning

Remove:

  • The accessories drive belt   (see the relevant operation)
  • The fastening bolts of the refrigeration compressor clutch
  • The clip securing the air conditioning pipes on the rear lifting plate

Move aside and suspend the air conditioning compressor on the side of the vehicle (Without opening the cooling circuit).

2.2. Subsequent operations

Lift and support the vehicle.

Detach and move aside:

  • The clutch slave cylinder (euro4)
  • The hydraulic stop (euro5)
  • The earth cable
  • The starter electrical supply
  • The gear control cables
Figure b2cm001d

Remove:

  • The air duct (7)
  • The air duct (9)
  • The bolts (10), (12)
  • The lower torque reaction link (11)
  • The power steering pump (8)   (see the relevant operation)

Move aside and suspend the power steering pump (8).

Put lifting table [3] together with its supports [2b], [2a] in position under the engine.

Lift the elevating platform [3].

2.3. Alternator side

Figure b1cm001d

Fit a support [2a] on a gearbox fixing.

Place another support [2a] in the drive shaft bearing (On the right-hand side).

2.4. Oil filter side

Figure b1cm002d

Position: The tools [2b] in the recess holes of the cylinder block.

3. Removing   (continued)

Figure b1hm001d

Remove:

  • The nuts (13)
  • The bolts (15)
  • The right-hand engine mounting (14)
Figure b1bm002d

Remove bolts (19).

Release: The earth braid (18).

Remove:

  • The bolts (16)
  • The nuts (17)
  • The left-hand engine mounting (20)
Figure c4am001d

CAUTION: Ensure that there is no fouling between the engine-gearbox assembly and the body.

Slowly lower the engine and gearbox assembly; Using the lifting table [3].

Manoevre the engine-gearbox assembly to facilitate removal.

Remove the power unit assembly   (from below).

Move the engine-gearbox assembly away from under the vehicle.

4. Refitting

Place the engine/gearbox assembly on the hydraulic table [3].

Figure c4am001d

CAUTION: Ensure that there is no fouling between the engine-gearbox assembly and the body. Manoevre the engine-gearbox assembly to facilitate its repositioning.

Refit the engine-gearbox assembly   (from underneath the vehicle).

Refit:

  • The left-hand engine mounting (20)
  • The nuts (17)
  • The bolts (16)

Position: The earth braid (18).

Refit bolt (19).

Refit:

  • The right-hand engine mounting (14)
  • The bolts (15)
  • The nuts (13)

Tighten:

  • The nuts (17) to 9,5 ± 0,5 daN.m
  • The bolts (16) to 9,5 ± 0,5 daN.m
  • The nuts (13) to 9,5 ± 0,5 daN.m
  • The bolts (15) to 9,5 ± 0,5 daN.m

Unclamp the power unit assembly from the lifting table [3].

Remove the tools [2a].

Withdraw the lifting bench [3] from under the vehicle.

Refit:

  • The lower torque reaction link (11)
  • The (10) bolt
  • The (12) bolt
  • The air duct (9)
  • The air duct (7)
  • The power steering pump (8) (see the relevant operation)

Tighten:

  • Screw (10) to 29 ± 1 daNm
  • Screw (12) to 29 ± 1 daNm

Position and couple up:

  • The gear control cables
  • The starter electrical supply
  • The earth cable
  • The hydraulic stop (euro5)
  • The clutch slave cylinder

Tighten the screws of the clutch slave cylinder to 2 ± 0,5 m.daN.

4.1. Vehicle with air conditioning

Position and fix: The air-conditioning compressor.

Tighten the bolts to 2,5 ± 0,25 daN.m.

Refit:

  • The bracket securing the air conditioning ducts on the lifting plate
  • The accessories drive belt   (see the relevant operation)

4.2. Subsequent operations

Reconnect the electrical harnesses (6).

Refit:

  • The air duct (5)
  • The air filter housing (4)
  • The braking assistance pipe (1)
  • The electrical harness shield (2)
  • The cover (3)

Reconnect the air flowmeter.

Couple up:

  • The fuel supply and return pipes
  • The expansion bottle pipe
  • The heater matrix inlet and outlet hoses
  • The turbocharger air cooler pipe   (right hand side)
  • The cooling radiator pipes

Refit:

  • The pre-catalytic converter   (see the relevant operation)
  • The drive shafts   (see the relevant operation)
  • The front wheels
  • The right-hand headlamp   (see the relevant operation)
  • The central section of the lower front panel   (see the relevant operation)
  • The protective panel under the engine

Fill and top up the level of the following of the following elements:

  • Engine
  • Gearbox   (see the relevant operation)
  • Cooling system   (see the relevant operation)

CAUTION: Perform the operations to be carried out following reconnection of the battery.

Reconnect the battery.

Start the engine.

Top up the coolant level (If necessary).

Remove the tool [1].

Return the vehicle to its wheels.

Carry out:

  • A road test
  • A reading of the diagnostic memories