Time Allowance
|
Number of cables |
Type 1 |
Type 2 |
Type 3 |
Type 4 |
Type 5 |
|
|
Repairing cables 1) |
Replacing plug casings |
Replacing individual spring-finger connectors |
Replacing plug casings and spring-finger connectors |
Replacing complete wiring harness plugs |
|
|
Time allowance |
|
1 |
.2 |
.1 |
.2 |
.2 |
.2 |
|
2 |
.4 |
|
.3 |
.4 |
.2 |
|
3 |
.6 |
.2 |
.5 |
.6 |
.4 |
|
4 |
.7 |
|
.6 |
.7 |
.5 |
|
5 |
.8 |
.2 |
.7 |
.9 |
.6 |
|
6 |
.9 |
|
.9 |
1.1 |
.7 |
|
7 |
1.1 |
|
1.1 |
1.3 |
.8 |
|
8 |
1.2 |
.3 |
1.2 |
1.5 |
.9 |
|
9 |
1.4 |
|
1.3 |
1.7 |
1.0 |
|
10 |
1.6 |
|
1.5 |
1.8 |
1.2 |
|
11 |
1.7 |
.4 |
1.7 |
2.0 |
1.2 |
|
12 |
1.9 |
|
1.8 |
2.2 |
1.3 |
1) Time allowances apply for repairs involving insertion of a cable section (two cable ends).
|
Number of cables |
Type 1 |
Type 2 |
Type 3 |
Type 4 |
Type 5 |
|
|
Repairing cables 1) |
Replacing plug casings |
Replacing individual spring-finger connectors |
Replacing plug casings and spring-finger connectors |
Replacing complete wiring harness plugs |
|
|
Time allowance |
|
13 |
2.0 |
|
1.9 |
2.4 |
1.5 |
|
14 |
2.2 |
.5 |
2.1 |
2.6 |
1.6 |
|
15 |
2.3 |
|
2.2 |
2.7 |
1.7 |
|
16 |
2.5 |
|
2.4 |
2.9 |
1.8 |
|
17 |
2.7 |
|
2.5 |
3.1 |
1.9 |
|
18 |
2.8 |
.6 |
2.7 |
3.2 |
2.1 |
|
19 |
2.9 |
|
2.8 |
3.5 |
2.2 |
|
20 |
3.1 |
|
3.0 |
3.7 |
2.2 |
|
21 |
3.2 |
|
3.1 |
3.8 |
2.4 |
|
22 |
3.4 |
.7 |
3.2 |
4.0 |
2.5 |
|
23 |
3.6 |
|
3.4 |
4.2 |
2.6 |
|
24 |
3.7 |
|
3.6 |
4.4 |
2.7 |
|
25 |
3.9 |
.7 |
3.7 |
4.6 |
2.8 |
|
26 |
4.0 |
|
3.8 |
4.7 |
2.9 |
1) Time allowances apply for repairs involving insertion of a cable section (two cable ends).
|
Number of cables |
Type 1 |
Type 2 |
Type 3 |
Type 4 |
Type 5 |
|
|
Repairing cables 1) |
Replacing plug casings |
Replacing individual spring-finger connectors |
Replacing plug casings and spring-finger connectors |
Replacing complete wiring harness plugs |
|
|
Time allowance |
|
27 |
4.2 |
|
4.0 |
4.9 |
3.1 |
|
28 |
4.3 |
.8 |
4.2 |
5.1 |
3.2 |
|
29 |
4.5 |
|
4.2 |
5.2 |
3.2 |
|
30 |
4.7 |
|
4.4 |
5.4 |
3.3 |
|
31 |
4.7 |
|
4.5 |
5.6 |
3.4 |
|
32 |
4.9 |
.9 |
4.7 |
5.7 |
3.5 |
|
33 |
5.0 |
|
4.7 |
5.9 |
3.7 |
|
34 |
5.1 |
|
4.9 |
6.1 |
3.7 |
|
35 |
5.2 |
|
5.1 |
6.2 |
3.8 |
|
36 |
5.3 |
1.0 |
5.2 |
6.4 |
3.9 |
|
37 |
5.5 |
|
5.3 |
6.6 |
4.0 |
|
38 |
5.6 |
|
5.4 |
6.7 |
4.1 |
|
39 |
5.7 |
1.1 |
5.6 |
6.9 |
4.2 |
|
40 |
5.8 |
|
5.7 |
7.1 |
4.3 |
1) Time allowances apply for repairs involving insertion of a cable section (two cable ends). When replacing spring-finger connectors with two or more cables, please increase the permissible time allowance by .2 hours per additional cable.
|
|
13 Electrical