Removing-refitting power unit (page 2 of 3)

Make
Fiat
Model
Bravo /Brava (182) Factory Service Manual
Year
1995–2001
Section
Removing-refitting (1370 12v)
10 EngineRemoving-refitting power unit · page 2 of 3
Diagram showing injection lead and front lead joints on the engine
Diagram showing reverse inhibition lead connection point and earth cable

  1. Disconnect both injection lead/front lead joints shown in the figure.
  2. Disconnect reverse inhibition lead from gearbox by undoing the screw shown in the figure and the earth cable.
  3. Undo nut (1) and lock-nut (2) to disconnect the clutch cable from the control lever.
  4. Disconnect the gear lever by undoing the nut shown in the figure.
  5. Disconnect the gear selection cable head, raise the retaining fork shown in the figure and place the assembly to one side in the engine bay.
Diagram showing clutch cable control lever with nuts labeled 1 and 2
Diagram showing gear lever mounting nut
Diagram showing gear selection cable head and retaining fork being raised

Parts & tools for this job For 1995 Fiat Bravo

Links open Amazon search results in a new tab. As an Amazon Associate I earn from qualifying purchases.