01 General information02 Specifications03 Manufacturing data and tolerances04 Tightening torques05 Fluids and lubricants06 Maintenance07 Diagnostic checks08 Engine09 Clutch10 Gearbox and differential11 Axles and driveshafts12 Brakes13 Steering14 Suspension and wheels15 Heating, air conditioning and auxiliary units16 Electrical equipment17 Body fittings18 Body panels and frame19 Wiring diagrams and electrical functions20 Wiring harnesses21 Connectors and pin-outs22 Fault diagnosis23 Special tools
Fiat Grande Punto Factory Service Manual (2005-2012)16 · Electrical equipment
16 · Electrical

Check battery charge status

Make
Fiat
Model
Grande Punto Factory Service Manual
Year
2005–2012
Section
Current generation › Check battery charge status
Electrical equipmentCheck battery charge status

CHECK BATTERY CHARGE STATUS

Check 5530BC

1.3 Multijet

STEPCHECK TO BE PERFORMEDRESOLUTION IF THE CHECK IS NOT OK
1Remove the battery cover. Check visually that the battery terminals are not oxidisedClean the layer of oxidation from the terminals
2The water gauge (magic eye) should not be white indicating that the electrolyte level is too low.

Replace the battery

Op. 5530B10 BATTERY - R+R

3The plugs or caps should not be damaged or incorrectly positioned

Replace the battery

Op. 5530B10 BATTERY - R+R

4There should be no damage to the main body of the battery, the cover or the terminalsReplace the battery
5There should be no signs of electrolyte escaping from the battery (wet areas or large salt deposits)Clean the area involved and top up to the correct level
6

Check that the vehicle has been unused for at least 30 minutes. Disconnect the negative terminal and check the charge status using the MICRO 360 instrument, part code 1806367006, making sure to perform the check by connecting directly to the battery terminals. The instrument must supply one of the following signals "CHARGE RETEST" OR "BATT. OK+RECHARGE" or the display will remain off.

Move on to Step 11

Move on to Step 7
7The equipment will give one of the following signals "REPLACE BATT." or "CELL SHORT". Go on to Step 10Move on to Step 8
8

Check the electrical connections for the supply circuit are correct with particular reference to the power supplies and earths

See E1010 POWER SUPPLY

Restore the correct connections

See E1010 POWER SUPPLY

9Reconnect or refit the battery on the vehicle and try and start the engine several times (at least 6 or 7) with about 4-5 seconds between each attempt. Ensure the start-ups are successful. The test may be considered to be concluded

Continue with Step 4 of the

See Test 5530B BATTERY AND LEADS

10

Replace the battery

Op. 5530B10 BATTERY - R+R

The test can be considered over

11Rechare the battery using tool 1806151001
12Check the charge status using a MICRO 360 gauge, tool code 1806367006, ensuring the test is carried by connecting directly to the battery terminals. The gauge must supply one of the following signals “CHARGE RETEST”, “REPLACE BATT.” or “CELL SHORT” or the display will remain off. Go on to Step 9Move on to Step 10