10 EngineRemoving - refitting · page 7 of 8
Diagram showing two bolts indicated by arrows on the bell housing, with icons indicating removal direction.
  1. Remove the bolts indicated from the bell housing in order to position the tool used to remove the power unit.
Diagram showing a hydraulic jack and mounting tools (labeled 1860859000 and 1860860000) positioned under the power unit.
  1. Position tool 1860860000 used to mount the power unit on the hydraulic jack and fasten to the power unit using the tools shown.

The hydraulic jack must have a capacity of at least 1000 kg and it must be sufficiently high to allow the power unit to be removed from below. When calculating the height, consider the maximum height setting of the lift and the minimum height setting of the hydraulic jack.

Diagram showing an arrow pointing to fastenings for the engine oil heat exchanger.
  1. Remove the engine oil heat exchanger from the fastenings shown, then secure to the power unit.

Parts & tools for this job For 1995 Fiat Bravo

Links open Amazon search results in a new tab. As an Amazon Associate I earn from qualifying purchases.